A 216 m² Saudi national pavilion at the 17th Trade Fair of the OIC Member States in Dakar, Senegal, 13–19 June 2022. It was delivered by the team that now designs and fabricates under the Echo Expo name.

The project

At 216 m², this is the second largest structure in our record, behind only the 228 m² nonwovens stand at INDEX in Geneva. It ran for seven days — roughly twice the length of a typical European trade fair — which changes almost every material decision on the build.

National pavilion at the OIC Member States Trade Fair in Dakar, with a continuous branded fascia over a row of identical booths, each with shelving, a counter, a screen and seating
The pavilion in Dakar — one continuous national fascia over identical booths, so no participant has a better position than another.

A national pavilion is a different brief from a stand

A company stand has one occupant and one message. A national pavilion hosts many companies under one identity, and the design has to hold both at once:

How equity between participants was actually built

The pavilion ran the national identity — the Saudi Made brand — as one continuous illuminated fascia band along the whole frontage, above a row of identically specified booths. Each participant received the same thing: a branded counter, wall shelving, a wall-mounted screen, a table and seating.

That is a deliberate answer to the hardest political problem in pavilion design. When every unit is identical, no allocation is a better allocation, and the organiser is not fielding complaints about who got the corner. The country reads as one exhibitor from the aisle, and each company still has a defensible space to stand in and talk.

What seven days changes

A three-day fair is survivable with finishes that are merely presentable. A seven-day event is not. Over a week, floor coverings show traffic lanes, counter edges chip, and anything that was touched up on site starts to show where it was touched up.

A longer run also means the pavilion must be maintainable while occupied: cleaning access, replenishment storage, and consumables that can be restocked without dismantling a display. Over 216 m² and seven days, storage stops being a cupboard and becomes part of the plan.

Building in West Africa

Working outside the established European fairgrounds changes the assumptions. Local material supply, hire stock, rigging services and skilled labour cannot be taken for granted the way they can at a major European venue, and the practical consequence is straightforward: what you do not bring, you may not get.

That argues for prefabrication, for shipping complete rather than in parts, and for carrying spares of the things that get damaged in transit. It is the same discipline that makes a stand reusable — build it to be assembled, not to be made.

Why it matters

This is our West Africa project and our largest national pavilion. Alongside our work in Kigali, Rwanda and our Casablanca workshop, it means our African experience is not theoretical.

Services delivered

Frequently asked questions

Do you build national and regional pavilions?

Yes, including a 216 m² national pavilion hosting multiple participating companies. Tell us the number of participants and whether positions are allocated or sold, because that determines the layout before anything else does.

Will you build outside Europe?

Yes. We have built in West Africa, East Africa, Morocco and the Middle East as well as across Europe. Outside the major fairgrounds we prefabricate and ship complete rather than relying on local supply.

Our event runs longer than a normal trade fair. Does that change the build?

Yes, materially. Specify harder-wearing floor and edge finishes, plan cleaning and replenishment access, and budget storage as part of the layout rather than an afterthought.