What counts as rigging
Anything suspended from the hall structure rather than supported from your floor: a hanging sign, a banner, a lighting truss, a ceiling raft, a fabric ring, speakers, screens. If the building holds it up, it is rigging and it needs approval. Things standing on your own floor are not rigging — even if they are tall. A four-metre tower bolted to a weighted base is a structure, judged under different rules.The five questions a venue will ask
- What is the total weight, and how is it distributed? Not an estimate. The venue signs off rigging on numbers.
- How many suspension points, and where? Halls have fixed rigging grids. Your points must land on the grid, not where the drawing wanted them.
- What is the height to the underside? Most halls cap how low a suspended element may hang, and many cap how high it may reach above the stand.
- Who is doing the rigging? Many venues insist their own appointed rigger does the work. You order it; you do not do it.
- Is it inside your stand footprint? Nothing may overhang a neighbour or an aisle.
The drawings the venue will ask for
- A plan showing suspension point positions with dimensions from two stand edges
- An elevation showing height to underside and overall top height
- A weight schedule per point and total
- A structural calculation or a statement from the fabricator for anything unusual
Why a suspended element is worth the paperwork
Height is the only way to catch the eye from the far end of an aisle. A stand reads from three metres; a suspended sign reads from thirty. For a stand in a row rather than an island, it is often the single highest-return item in the build. At interzum Cologne we hung a halo sign above a 76.5 m² stand for Durian Laminates. At SIMAC Tanning Tech in Milan it was a suspended fascia box over a slatted ceiling raft. We drew, weighed and cleared both before anyone cut a panel.When the venue refuses rigging, and what to do instead
Refusals are usually one of: the hall has no grid above your stand, your points fall outside the footprint, the weight exceeds what that grid section carries, or the order arrived after the deadline. The fallback is a self-supporting gantry — a portal or tower carrying the sign from your own floor. It costs more in material and takes longer to build, but it needs no rigging approval at all. Designing the gantry as an option from the start is cheap insurance; designing it in a panic on site is not.Deadlines
Rigging orders close early, typically three to six weeks out, and late requests carry a surcharge where they are accepted at all. Treat the rigging deadline as the real design deadline for anything above head height. The same logic applies to your electrical connection — suspended lighting draws power, and both orders go in together.How we handle it
On every project, we draw, weigh and submit rigging as part of the venue paperwork, alongside floor loading and electrical declarations. We never leave clients to negotiate with a rigging desk in a language they do not speak. Send us the stand details and tell us what you want in the air. Related: How we build · Where to save money on a stand · Documented projectsPart of the exhibitor guide series. Start with the technical manual checklist — eleven things with deadlines attached.
Frequently Asked Questions
What is a suspended structure on a stand?
A banner, truss or lighting rig hung from the hall ceiling above the stand, used to make the stand visible from a distance.
Do suspended structures need approval?
Yes. Organisers require drawings and load details in advance, and the rigging points are usually installed by the venue’s official rigger.
How far ahead should rigging be ordered?
By the deadline in the exhibitor manual, which is often several weeks before build-up. We include it in the project plan from the start.
Can every hall take a suspended banner?
No. Some halls or areas have limited rigging points or height rules, so we check the venue’s plan before designing anything overhead.